pipeline renewal

Options for Gas Main Replacement

For a cast-iron natural gas main, initial replacement options for Peoples Gas in Chicago seemed straightforward—plastic or steel pipes. Logistical, operational and system constraints led the utility to explore an alternative solution: trenchless pipe-lining technology.

Engineering Innovations Emerge from Lining Challenges

The 30-inch turnkey project in Brooklyn’s Gowanus Canal challenged what we thought was possible. There were several times we wondered, can it be done? There was nothing conventional about this project. The drawings showed a pipe configuration I had never seen.

Eversource Evaluates Trenchless Technology

Eversource Engineers analyze PPM’s CIPL for a capstone project to rehabilitate a leaking bridge pipeline. Read about the role of trenchless technologies in Eversource’s portfolio of solutions for improving safety, reliability, repairing leaks and reducing fugitive emissions.

BEM Pipeline Assessment For Railroad Crossing

Assessing ferrous pipe walls provides critical data to determine the condition and integrity of pipelines. When a utility needed to assess a section of a 20 inch cast iron main that runs under a railroad right-of-way, Broadband Electromagnetic Probe (BEM) accurately assessed the condition and the degree of corrosion or graphitization.

SUPPORTING OPERATORS AS THEY IMPLEMENT THE 2020 PIPES ACT

The 2020 PIPES ACT incorporates new regulatory requirements that formalize and amplify emission reduction as a component of pipeline safety. Bob Wilson shares tools, technology and practices to consider as operators integrate the mandates into their day-to-day operations.

Bridges to No Repair

In 30 years, I haven’t met a utility that didn’t have pipelines along bridges in their inventory. As bridges age, so do the pipelines. We are all getting older. Over forty percent of the bridges in the US are over fifty years old. In the Northeast, gas pipelines and bridges are typically 75 - 100 years old.

World Record 42-Inch Gas Main CIPL

Records are made to be broken, and the world record CIPL in summer 2019 of a 42-Inch Cast Iron Gas Main in a complex layout buried under eight lanes of the Garden State Parkway in East Orange NJ was a breakthrough technological achievement building upon past experience, and fresh technical innovations. It was possible because of lessons learned in overcoming challenges on previous CIPL projects renewing progressively larger diameter CI gas mains.